EICR for a housing association property in Redditch

EICR Testing in Redditch

Share This Post

Project overview

We completed an EICR for a housing association property in Redditch, working as an NICEIC Approved Contractor (registration number 613373000). The installation, estimated at 35 years old, had no previous records, so we carried out a full inspection and testing process. After identifying and completing the necessary remedial work, we confirmed the installation was safe and compliant for continued use. The inspection was carried out by Ryan Ward, our Managing Director, who brings 15 years’ experience and holds City & Guilds 2394, 2395, Level 3 Electrical Installation and 18th Edition Wiring Regulations qualifications.

Client requirement

The property’s recommended inspection date had passed, and the housing association required an up-to-date EICR to demonstrate compliance and ensure the installation was safe for ongoing use. With no previous reports or records available, we needed to establish the installation’s condition from first principles.

Our role

We inspected and tested the entire property, which is supplied via a single consumer unit above the kitchen doorway. This included checking the supply intake, consumer unit, earthing and bonding arrangements, and all wiring, including the main earthing conductor and bonding to gas and water services. We also reviewed areas that had been altered or extended around 10 years ago to ensure all parts of the installation were covered.

Testing covered seven circuits: smoke alarms, shower, sockets, cooker, upstairs heater, and separate lighting circuits for upstairs and downstairs. We isolated the supply and unplugged appliances to carry out the tests safely. Insulation resistance readings were above 999 megohms on every circuit, polarity was correct throughout, and the RCDs operated within 29 to 31 milliseconds, well inside the 300 millisecond requirement.

Challenges

With an installation of this age and no previous records, every aspect had to be assessed directly against BS 7671 standards. Where cables were concealed in walls or under floors and could not be visually inspected, we recorded these as limitations in the report, as required by the regulations.

Findings and remedial work

The installation showed signs of age, so we completed remedial work before issuing the report. Once this was done, we confirmed the installation met current regulations and was suitable for continued use.

We also raised three C3 observations, which are recommendations for improvement rather than faults. These do not affect the satisfactory outcome of the report.

The consumer unit is plastic, so we recommended upgrading to a metal enclosure to meet current requirements for non-combustible consumer units in homes. The RCDs are Type AC, and we advised changing them to Type A, which also responds to the pulsating DC produced by some modern electronic equipment. We also noted the absence of a surge protective device (SPD), which would help protect the installation and connected equipment from voltage surges.

We can provide a fixed price quotation for these recommended improvements if required.

Outcome

The installation was confirmed as satisfactory for continued use. The housing association now has a current EICR on file, with the three C3 recommendations clearly recorded for future planning. The next inspection is recommended for September 2031.

If you manage residential properties and have inspections due, let us know your requirements and we’ll advise on the best next steps. Contact us on 0121 272 7472 to discuss your properties.

More To Explore

EICR Testing in Redditch

EICR for a housing association property in Redditch

Project overview We completed an EICR for a housing association property in Redditch, working as an NICEIC Approved Contractor (registration number 613373000). The installation, estimated

Need Our Services?

Get in touch by clicking the button below